Installation
Installation sequence
-
Fix a 60mm thick timber stop batten across the rafters at eaves (A).
-
Lay ROOFMATE™ RL-X boards with long edges at right angles to the rafters and with the tongue pointing up the slope (B).
-
Butt the first row of boards tight against the stop batten. Continue laying up the slope towards the ridge. At ridge butt ROOFMATE RL-X to the ridge board (B) or to ROOFMATE RL-X on the opposite slope. (C).
-
Fix ROOFMATE-RL-X boards temporarily by occasional nailing until permanently secured by the counter battens.
-
At all cut edges, junctions and penetrations trim ROOFMATE RL-X boards neatly to fit (D) (E). Seal any gaps with polyurethane foam.
-
Either: (a) lay the underlay directly onto the ROOFMATE RL-X boards and secure with counter battens; or (b) secure the ROOFMATE RL-X boards with counter battens, then drape the underlay over the counter battens and secure with tiling/slating battens. (Refer to underlay supplier’s instructions).
-
Fit ROOFMATE RL-X boards cut-to-size between the rafters from within the loft space. Press tight against the ROOFMATE RL-X boards and fix by nailing support battens to the rafters (F).



Key points
-
-
Cut and fit boards neatly.
-
Seal any gaps, particularly at cut joints.
-
Do not stand on ROOFMATE RL-X or use as a working platform.
|
|